Syracuse University Project Management at Mm2 Case Study Discussion Questions Read the Project Management at MM Case Study in the uploaded document. Answer the Discussion Questions at the end of the Case Study.Your responses must be complete, detailed and in APA format. All work must be 2 FULL pages, single spaced, 12 font Times New Roman. The cover and reference page must be on separate pages. Please DO NOT include the question in your work as only your findings should be submitted. Please add at least 5 references. MINI CASE
Project Management at MM2
“We’ve got a real ‘warm puppy’ here,” Brian Smith told Werner McCann. “Make sure
you make the most of it. We could use a winner.”
Smith was MM’s CIO, and McCann was his top project manager. The puppy in
question was MM’s new venture into direct-to-customer marketing of its green meters, a
product designed to help better manage electrical consumption, and the term referred
to the project’s wide appeal. The strategy had been a hit with analysts ever since it had
been revealed to the financial community, and the company’s stock was doing extremely
well as a result. “At last,” one had written in his popular newsletter, “we have a company that is willing to put power literally and figuratively in consumers’ hands. If MM
can deliver on its promises, we fully expect this company to reap the rewards.”
Needless to say, the Green project was popular internally, too. “I’m giving it to you
because you have the most project-management experience we’ve got,” Smith had said.
“There’s a lot riding on this one.” As he walked away from Smith’s office, McCann wasn’t
sure whether to feel complimented or terrified. He had certainly managed some successful projects for the company (previously known as ModMeters) over the past five years
but never anything like this one. That’s the problem with project management, he thought. In
IT almost every project is completely different. Experience only takes you part of the way.
And Green was different. It was the first truly enterprisewide project the company had ever done, and McCann was having conniptions as he thought about telling
Fred Tompkins, the powerful head of manufacturing, that he might not be able to have
everything his own way. McCann knew that, to be successful, this project had to take an
outside-in approach—that is, to take the end customers’ point of view on the company.
That meant integrating marketing, ordering, manufacturing, shipping, and service
into one seamless process that wouldn’t bounce the customer from one department to
another in the company. MM had always had separate systems for each of its “silos,”
and this project would work against the company’s traditional culture and processes.
The Green project was also going to have to integrate with IT’s information management renewal (IMR) project. Separate silos had always meant separate databases, and
the IMR project was supposed to resolve inconsistencies among them and provide
accurate and integrated information to different parts of the company. This was a huge
political challenge, but, unless it worked, McCann couldn’t deliver on his mandate.
Then there was the issue of resources. McCann groaned at the thought. MM had
some good people but not enough to get through all of the projects in the IT plan within
the promised timelines. Because of the importance of the Green project, he knew he’d
get good cooperation on staffing, but the fact remained that he would have to go outside for some of the technical skills he needed to get the job done. Finally, there was the
schedule that had to be met. Somehow, during the preliminary assessment phase, it
2
Smith, H. A., and J. D. McKeen. “Project Management at MM.” #1-L05-1-009, Queen’s School of Business,
November 2005. Reproduced by permission of Queen’s University, School of Business, Kingston, Ontario.
324
Project Management at MM
had become clear that September 5 was to be the “hard launch” date. There were good
reasons for this—the fall was when consumers usually became concerned with their
energy consumption—but McCann worried that a date barely twelve months from now
would put too much pressure on his team. “We’ve got to get in there first, before the
competition,” Smith had said to him. “The board expects us to deliver. You’ve got my
backing and the support of the full executive team, but you have to deliver this one.”
SIX WEEKS LATER
It was full steam ahead on the Green project. It’s amazing what a board mandate and
executive sponsorship can do for a project, thought McCann, who knew how hard it usually was to get business attention to IT initiatives. He now had a full-time business counterpart, Raj Sambamurthy. Samba, as he was known to his colleagues, had come out of
Tompkins’s division and was doing a fantastic job of getting the right people in the room
to make the decisions they needed to move ahead. The Green steering committee was no
Mickey Mouse group either. Smith, Tompkins, and every VP affected by the project were
meeting biweekly with him and Samba to review every aspect of the project’s progress.
McCann had pulled no punches when communicating with the committee.
“You’ve given me the mandate and the budget to get this project off the ground,” he had
told them. “But we have to be clear about what we’re trying to accomplish.” Together,
they had hammered out a value proposition that emphasized the strategic value of the
project and some of the measures they would use to monitor its ultimate success. The
requirements and design phase had also gone smoothly because everyone was so motivated to ensure the project’s success. “Linking success to all our annual bonuses sure
helped that!” McCann had remarked wryly to Samba.
Now McCann was beginning to pull together his dream team of implementers.
The team had chosen a package known as Web-4-U as the front end of the project, but it
would take a lot of work to customize it to suit their unique product and, even more, to
integrate it with MM’s outmoded back-end systems. The Web-4-U company was based
in Ireland but had promised to provide 24/7 consultation on an as-needed basis. In
addition, Samba had now assembled a small team of business analysts to work on the
business processes they would need. They were working out of the firm’s Cloverdale
office, a thirty-minute drive from IT’s downtown location. (It was a shame they couldn’t
all be together, but space was at a premium at headquarters. McCann made a mental
note to look into some new collaboration software he’d heard about.) Now that these
two pieces were in place, McCann felt free to focus on the technical “guts” of the system. “Maybe this will work out after all,” he said.
THREE MONTHS TO LAUNCH DATE
By June, however, McCann was tearing out what little hair was left on his head. He
was seriously considering moving to a remote Peruvian hamlet and breeding llamas.
“Anything would be better than this mess,” he told Yung Lee, the senior IT architect,
over coffee. They were poring over the project’s critical path. “The way I see it,” Lee
stated matter-of-factly, “we have two choices: We can continue with this inferior technology and meet our deadline but not deliver on our functionality, or we can redo the
plan and go back to the steering committee with a revised delivery date and budget.”
325
326
4FDUJPO*7 r *51PSUGPMJP%FWFMPQNFOUBOE.BOBHFNFOU
McCann sighed. Techies always saw things in black and white, but his world
contained much more gray. And so much was riding on this—credibility (his, IT’s, the
company’s), competitiveness, and stock price. He dreaded being the bearer of this bad
news, so he said, “Let’s go over this one more time.”
“It’s not going to get any better, but here goes.” Lee took a deep breath. “Web-4-U
is based on outmoded technology. It was the best available last year, but this year the
industry has agreed on a new standard, and if we persist in using Web-4-U, we are
going to be out of date before Green even hits the street. We need to go back and completely rethink our technical approach based on the new standard and then redesign
our Web interface. I know it’s a setback and expensive, but it has to be done.”
“How come we didn’t know about this earlier?” McCann demanded.
Lee replied, “When the standard was announced, we didn’t realize what the
implications were at first. It was only in our quarterly architecture meeting that the
subject came up. That’s why I’m here now.” The architects were a breed apart, thought
McCann. All tech and no business sense. They’d lost almost three months because of
this. “By the way,” Lee concluded, “Web-4-U knew about this, too. They’re scrambling
to rewrite their code. I guess they figured if you didn’t know right away, there would be
more chance of you sticking with them.”
The chances of that are slim to none, thought McCann. His next software provider,
whoever that was, was going to be sitting right here under his steely gaze. Seeing an
agitated Wendy Chan at his door, he brought the meeting to a hasty close. “I’m going
to have to discuss this with Brian,” he told Lee. “We can’t surprise him with this at the
steering committee meeting. Hang tight for a couple of days, and I’ll get back to you.”
“OK,” said Lee, “but remember that we’re wasting time.”
Easy for you to say, thought McCann as he gestured Chan into his office. She was
his counterpart at the IMR project, and they had always had a good working relationship.
“I just wanted to give you a heads-up that we’ve got a serious problem at IMR that will
affect you,” she began. Llamas began prancing into his mind’s eye. “Tompkins is refusing to switch to our new data dictionary. We’ve spent months hammering this out with
the team, but he says he wasn’t kept informed about the implications of the changes, and
now he’s refusing to play ball. I don’t know how he could say that. He’s had a rep on the
team from the beginning, and we’ve been sending him regular progress reports.”
McCann was copied on those reports. Their pages of techno-jargon would put
anyone to sleep! He was sure that Tompkins had never got past the first page of any of
those reports. His rep was a dweeb, too, someone Tompkins thought he could live without in his daily operations.
“Damn! This is something I don’t need.” Like all IT guys, McCann hated corporate politics with a passion. He didn’t understand them and wasn’t good at them. Why
hadn’t Samba and his team picked up on this? They were plugged into the business.
Now he was going to have to deal with Chan’s problem as well as his own if he wanted
to get the Green project going. Their back-end processes wouldn’t work at all unless
everyone was using the same information in the same format. Why couldn’t Tompkins
see that? Did he want the Green project to fail?
“The best way to deal with this one,” advised Chan, “is to force him to accept
these changes. Go to John Johnson and tell him that you need Tompkins to change his
business processes to fit our data dictionary. It’s for the good of the company, after all.”
Chan’s strong suit wasn’t her political savvy.
Project Management at MM
“You’re right that we need Tompkins on our side,” said McCann, “but there may
be a better way. Let me talk to Samba. He’s got his ear to the ground in the business.
I’ll speak with him and get back to you.”
After a bit of chitchat, Wendy Chan left McCann to his PERT chart, trying again
to determine the extra cost in time if they went with the new technology. Just then
the phone rang. It was Linda Perkins, McCann’s newly hired work-at-home usability
designer. She was one of the best in the business, and he was lucky to have snagged her
just coming off maternity leave. His promise of flexible working hours and full benefits
had lured her back to work two months before her year-long leave ended. “You’ve got
to do something about your HR department!” Perkins announced. “They’ve just told
me that I’m not eligible for health and dental benefits because I don’t work on the premises! Furthermore, they want to classify me as contingent staff, not managerial, because
I don’t fit in one of their petty little categories for employees. You promised me that you
had covered all this before I took the job! I gave up a good job at LifeCo so I could work
from home.”
McCann had indeed covered this issue in principle with Rick Morrow, IT’s HR
representative, but that had been almost eight months ago. Morrow had since left the
firm. McCann wondered if he had left any paperwork on this matter. The HR IT spot
had not yet been filled, and all of the IT managers were upset about HR’s unreceptive
attitude when it came to adapting its policies to the realities of today’s IT world. “OK,
Linda, just hang in there for a day or two and I’ll get this all sorted out,” he promised.
“How’s the usability testing coming along?”
“That’s another thing I wanted to talk with you about. The team’s making changes
to the look and feel of the product without consulting me,” she fumed. “I can’t do my
job without being in the loop. You have to make them tell me when they’re doing things
like this.”
McCann sighed. Getting Perkins on the project had been such a coup that he
hadn’t given much thought to how the lines of communication would work within
such a large team. “I hear you, Linda, and we’ll work this out. Can you just give me a
few days to figure out how we can improve things?”
Hanging up, he grabbed his jacket and slunk out of the office as quickly as he
could before any other problems could present themselves. If he just kept walking
south, he’d make it to the Andes in three, maybe four, months. He could teach himself Spanish along the way. At least the llamas would appreciate his efforts! MM could
take its project and give it to some other poor schmuck. No way was he going back! He
walked furiously down the street, mentally ticking off the reasons he had been a fool to
fall for Smith’s sweet talk. Then, unbidden, a plan of attack formed in his head. Walking
always did the trick. Getting out of the office cleared his head and focused his priorities.
He turned back the way he had come, now eager to get back in the fray. He had some
things to do right away, and others he had to put in place ASAP.
Discussion Questions
1. Some organizational factors increase a project’s likelihood of success. Identify these
“facilitators” for the Green project.
2. Other organizational factors decrease a project’s likelihood of success. Identify these
“barriers” for the Green project.
3. Outline the things that McCann needs to do right away.
327

Purchase answer to see full
attachment

Don't use plagiarized sources. Get Your Custom Essay on
Syracuse University Project Management at Mm2 Case Study Discussion Questions Read the Project Management at MM Case Study in the uploaded document. Answer
Just from $13/Page
Order Essay
Homework On Time
Calculate the Price of your PAPER Now
Pages (550 words)
Approximate price: -

Why Choose Us

Top quality papers

We always make sure that writers follow all your instructions precisely. You can choose your academic level: high school, college/university or professional, and we will assign a writer who has a respective degree.

Professional academic writers

We have hired a team of professional writers experienced in academic and business writing. Most of them are native speakers and PhD holders able to take care of any assignment you need help with.

Free revisions

If you feel that we missed something, send the order for a free revision. You will have 10 days to send the order for revision after you receive the final paper. You can either do it on your own after signing in to your personal account or by contacting our support.

On-time delivery

All papers are always delivered on time. In case we need more time to master your paper, we may contact you regarding the deadline extension. In case you cannot provide us with more time, a 100% refund is guaranteed.

Original & confidential

We use several checkers to make sure that all papers you receive are plagiarism-free. Our editors carefully go through all in-text citations. We also promise full confidentiality in all our services.

24/7 Customer Support

Our support agents are available 24 hours a day 7 days a week and committed to providing you with the best customer experience. Get in touch whenever you need any assistance.

Try it now!

Calculate the price of your order

Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

No need to work on your paper at night. Sleep tight, we will cover your back. We offer all kinds of writing services.

Essays

Essay Writing Service

You are welcome to choose your academic level and the type of your paper. Our academic experts will gladly help you with essays, case studies, research papers and other assignments.

Admissions

Admission help & business writing

You can be positive that we will be here 24/7 to help you get accepted to the Master’s program at the TOP-universities or help you get a well-paid position.

Reviews

Editing your paper

Our academic writers and editors will help you submit a well-structured and organized paper just on time. We will ensure that your final paper is of the highest quality and absolutely free of mistakes.

Reviews

Revising your paper

Our academic writers and editors will help you with unlimited number of revisions in case you need any customization of your academic papers